PROCESS TO OBTAIN A BUILDING PERMIT FROM THE KWAHU WEST MUNICIPAL ASSEMBLY
1. Get your site plan from the land owner (5 sets)
2. Get a title from the lands commission or lands title registry (where applicable).
3. Get an architect/ draughtsman to drawn up your building plan or consult Town and Country
Planning Unit
4. Buy forms at the Physical Planning Department (PPD) formerly Town and Country Planning
Department and building permit application jacket from the Finance Department.
5. Fill the form with the help of Municipal Town Planning office or Works Department.
6. You will be told of the required processing fees.
7. A day will be set for site inspection.
8. The Technical Sub-Committee will visit the site and request for changes where applicable.
9. Final form is submitted with the architectural drawings and other documents
10. Permit will be granted after the meetings of the Technical Sub-Committee and the Spatial Planning
Committee respectively.
11. The process takes about 2-3 months after submission of application